Project settings
External-facing toggles, live updates
Capital marketplace
Off
Off, no listing in market
Client visibility profile
Standard
Preview client view
Read-only sandbox
Budget vs. actual by trade
3 over
2 flagged
3 on budget
Spend burn, planned vs. actual
18 weeks
Actual
Planned
Validation alerts
1 critical
1 warning
Driveway concrete over benchmark
$15,600 actual is 71% over the $9,100 regional benchmark for this home type.
Framing under budget, verify
Framing trade is $14,200 under budget. Verify all line items are entered.
Insulation, no transactions
Log shows insulation started 6 days ago. No transactions recorded.
Project milestones
Day 84 of ~165
Site and foundation
Done
Framing
Done
Rough-ins
In progress
Now
Insulation, finishes, certificate
Pending
—
Start: Jan 29, 2026
Est. complete: Jul 12, 2026
Draw #: 3 of 6
Next draw: Apr 28, 2026
Recent activity
View all
TK
Lien waiver requested
Draw #3 from TK Concrete
9:14 AM
JM
Validation acknowledged
Driveway overage flagged for review
Yesterday
RH
Daily log submitted
R. Hawkins · 3 crews on site, rough-in progressing
Yesterday
JM
Roofing marked complete
$18,200 final cost
Apr 19
BW
Transaction posted
Blue Ridge Plumbing $4,200 rough-in
Apr 18
Task summary
View board
Next due: Submit Draw #3 · Apr 28
Loan snapshot
Draw #3 pending
LenderFirst TN Bank
Original amount$344,200
Drawn to date$248,000 (72%)
Interest rate6.75%
Accrued interest$18,200
Retainage held$24,800