Phase 4 of 8 · Framing

Foundation poured, framing crew on site this week.

Stratford Custom Homes wrapped the foundation walls Friday and started framing the first floor Monday. Next milestone is roof dry-in, scheduled for June 12.

Site prep complete Foundation complete Framing in progress Roof & dry-in Mechanical rough-in
Site photo · May 16
14 photos this week View all
Build Progress
38%
Day 142 of ~310
Spent to date
$163,495
38% of $430,250 contract
Next draw
$24,800
Draw 4 · pending lender
Target completion
Nov 8
Original target Nov 6
Recent updates See all
Framing crew started first floor walls
Posted by Marcus Hale · today, 8:14 AM · 6 photos
Today
Inspection passed: foundation
Loudon County inspector · Friday 2:30 PM
3 days ago
Draw 3 approved by First Tennessee
$32,150 released for foundation phase
5 days ago
Plans revision uploaded: A-201 framing
Open the documents tab for the latest revision
1 wk ago
Draws & payments View ledger
Draw 1 · Site prep
$22,400
Draw 2 · Foundation
$48,300
Draw 3 · Foundation 2
$32,150
Draw 4 · Framing
$24,800
Released to date $102,850 of $430,250
Your project team
MH SG RP JT +3
Stratford Custom Homes
MH
Marcus Hale
Builder · primary contact
MessageSend Marcus a message
SG
Sarah Gentry
Selections coordinator
MessageSend Sarah a message
RP
Rachel Pham
First Tennessee · construction lender
Read-only