Inspection-to-draw gate 3 of 4 inspections passed
Foundation
Passed Mar 5, 2026
Inspector: TN-IBC #5024
Framing
Passed Apr 8, 2026
Lender pre-draw walk: Apr 21
Rough-in MEP
Passed Apr 21, 2026
Plumbing, electrical, HVAC
Insulation
Scheduled May 4, 2026
Required before Draw #4
Gate status: Draw #3 unblocked. Insulation inspection must pass before Draw #4 can be submitted. View inspection schedule
Application no.
#3 of 6
Application date
April 23, 2026
Period to
April 28, 2026
Project
926 Stratford Ave
Owner
Stratford Builds LLC
Lender
First Tennessee Construction Lending
AIA G703, continuation sheet Application and certificate for payment
A. Item B. Description C. Scheduled value D. Previous E. This period F. Materials G. Total (D+E+F) H. % I. Balance J. Retainage (10%)
01 Site work & lot $37,600$37,600$0$0 $37,600100%$0$3,760
02 Foundation & slab $29,200$29,200$0$0 $29,200100%$0$2,920
03 Framing MC-2026-014 $52,000$38,200$0$0 $38,20073%$13,800$3,820
04 Roofing $18,200$0$18,200$0 $18,200100%$0$1,820
05 Rough-in MEP MC-2026-022 $38,400$0$22,500$0 $22,50059%$15,900$2,250
06 Exterior & siding $22,400$0$19,800$5,000 $24,800111%$0$2,480
07 Driveway & flatwork MC-2026-031 $9,100$0$15,600$0 $15,600171%$0$1,560
08 Insulation $8,800$0$0$0 $00%$8,800$0
Totals $215,700 $105,000 $76,100 $5,000 $186,100 86% $38,500 $18,610
Draw summary
Original contract value$215,700
Change orders (net)+$6,500
Adjusted contract$222,200

Total completed to date$186,100
Less retainage (10%)($18,610)
Less prior draws($105,000)
This draw$62,490
Lien waivers
Appalachian RoofingSigned
Cherokee FoundationSigned
Summit Framing LLCSent
TK ConcretePending
Ridgeline ExteriorsPending
Manage lien waivers