Total budget
$189,800
After 4 approved COs
Actual to date
$177,100
93% committed
Net variance
+$12,700
3 trades over benchmark
Marketplace locked
$25,896
14 lines via MC-2026-014
All rows 42 Marketplace 14 Internal vendor 21 Unassigned 7
Trades
F
Framing
$52,000 budgeted
Under
S
Site work
$12,400 budgeted
On
Fd
Foundation
$28,500 budgeted
Over
R
Roofing
$18,200 budgeted
On
Ri
Rough-ins
$38,400 budgeted
Over
I
Insulation
$8,800 budgeted
No txns
E
Exterior
$22,400 budgeted
Over
D
Driveway and concrete
$9,100 budgeted
+71%
Framing Marketplace MC-2026-014
Summit Framing LLC · Contract FR-2026-03 · via BuilderGrid marketplace
$14,200 under budget
Open to bid
DescriptionSourceQtyUnitUnit priceExtendedActualVarianceBenchmark
Locked by MC-2026-014 Exterior wall framing Marketplace · Summit 1,784SF$6.20$11,061$11,061$0 $5.80 to $7.00/SF
Locked by MC-2026-014 Interior wall framing Marketplace · Summit 1,784SF$2.80$4,995$4,995$0 $2.50 to $3.20/SF
Locked by MC-2026-014 Roof trusses (engineered) Marketplace · Summit 12EA$820$9,840$9,840$0 $700 to $950/EA
LVL beams · main span Internal · 84 Lumber 3EA$1,400$4,200$4,200$0 $1,100 to $1,600/EA
Sheathing · OSB 7/16" Internal · 84 Lumber 86SH$28$2,408$2,640+$232 $24 to $27/SH
Misc framing labor and supervision Internal · Summit 1LOT$5,904$5,904$5,904$0 $5.5k to $7k
Trade total $38,408 $38,640 +$232
Active marketplace contracts
3
MC
MC-2026-014 · Summit Framing LLC
Framing · 5 lines locked · $25,896 of $32,058 drawn
MC
MC-2026-022 · Blue Ridge Plumbing
Rough-ins · 3 lines locked · $12,400 drawn
MC
MC-2026-031 · TK Concrete
Foundation, driveway · 2 lines locked · $24,200 drawn
Recent budget activity
CO
CO-004 approved · +$2,840
Roofing · ridge vent upgrade
Apr 12
MC
MC-2026-022 signed
Blue Ridge Plumbing locked in
Apr 8
!
Driveway over benchmark
Flagged 71% above regional benchmark
Apr 4