6 Open Items
Master Bath
1 Critical
1 Open
📷
Missing vent stack fitting,PVC 3" connector
Plumbing rough-in cannot be completed until part is sourced. Blue Ridge Plumbing is tracking down locally.
Open
Added Apr 23
📷
Verify shower niche blocking is correctly positioned
Owner spec calls for niche at 54" AFF. Verify before insulation goes in,blocking cannot be moved after drywall.
Open
Added Apr 20
Kitchen
1 Verified
1 In Progress
1 Open
✓
Island electrical rough-in,verify 3 circuits
Verified by JM on Apr 19. Volunteer Electric confirmed 3 dedicated circuits installed per spec.
✓ Verified
Apr 19, 2026
▶
Range hood duct stub-out,position per kitchen plan
Mountain HVAC is placing the 6" round duct stub at 18" from ceiling per spec. In progress during today's HVAC rough-in.
In Progress
Added Apr 22
📷
Pantry wall,confirm blocking for adjustable shelving
Owner wants adjustable wire shelving in pantry. Confirm 3/4" OSB backing is installed in wall cavity before drywall.
Open
Added Apr 18
Garage
1 Open
📷
Garage door header,verify LVL size matches structural plan
Structural plan calls for double 1-3/4" x 9-1/2" LVL. Framing appears to show a single 9-1/2" LVL. Engineer to verify before sheathing.
Open
Added Apr 21
Floorplan,Pinned Punch Items
Open full floorplan view ›
Legend:
Open
In progress