Total Items
8
3 rooms
Open
6
Needs attention
In Progress
1
Verified
1
Master Bath
1 Critical 1 Open
📷
Missing vent stack fitting,PVC 3" connector
Plumbing rough-in cannot be completed until part is sourced. Blue Ridge Plumbing is tracking down locally.
Critical Rough-Ins Blue Ridge Plumbing
Open
Added Apr 23
📷
Verify shower niche blocking is correctly positioned
Owner spec calls for niche at 54" AFF. Verify before insulation goes in,blocking cannot be moved after drywall.
High Framing
Open
Added Apr 20
Kitchen
1 Verified 1 In Progress 1 Open
Island electrical rough-in,verify 3 circuits
Verified by JM on Apr 19. Volunteer Electric confirmed 3 dedicated circuits installed per spec.
Rough-Ins Volunteer Electric
✓ Verified
Apr 19, 2026
Range hood duct stub-out,position per kitchen plan
Mountain HVAC is placing the 6" round duct stub at 18" from ceiling per spec. In progress during today's HVAC rough-in.
HVAC Mountain HVAC
In Progress
Added Apr 22
📷
Pantry wall,confirm blocking for adjustable shelving
Owner wants adjustable wire shelving in pantry. Confirm 3/4" OSB backing is installed in wall cavity before drywall.
Medium Framing Summit Framing
Open
Added Apr 18
Garage 1 Open
📷
Garage door header,verify LVL size matches structural plan
Structural plan calls for double 1-3/4" x 9-1/2" LVL. Framing appears to show a single 9-1/2" LVL. Engineer to verify before sheathing.
Critical Framing Summit Framing
Open
Added Apr 21
Floorplan,Pinned Punch Items Open full floorplan view ›
Hover a pin to peek · click for full detail
Legend: Open In progress Verified