Thu, Apr 23, 2026
Conditions
Field Work Day
?
Pulled from National Weather Service for ZIP 37874 (Sweetwater TN). Refreshed at 5:30 AM each field-work day. Override the snapshot with the “Edit weather” action below.
⛅
Partly Cloudy
High Temp
68°F
Low Temp
51°F
Wind
12 mph
Precip.
0.00
Source: NWS Morristown TN office · pulled 5:30 AM
Day Summary
3
Crews
7
Workers
8h
Hours
Entered by: R. Hawkins · Submitted 5:48 PM
Crew on Site
| Trade | Company | Head Count | Supervisor |
|---|---|---|---|
| Rough-Ins | Blue Ridge Plumbing | 3 | D. Watkins |
| Rough-Ins | Mountain HVAC Services | 2 | A. Nguyen |
| Insulation | Valley Insulation Inc. | 2 | P. Garrett |
| Total | 7 workers | ||
Issues & Notes1 Issue
Plumbing, Missing Vent Stack Fitting
Blue Ridge Plumbing is missing a 3" PVC vent stack fitting for the master bath. Will need to order, estimated 1-day delay to rough-in completion if not sourced locally.
Valley Insulation completed exterior walls in master bedroom and living room. Will return tomorrow to finish remaining bays and attic floor. No issues.
Work Performed
Blue Ridge Plumbing
Completed rough-in plumbing for master bath and hall bath. Set water supply lines (PEX) for both bathrooms and kitchen. Installed drain, waste, and vent (DWV) stack through first floor. Still need vent stack fitting for master bath, see issues.
Mountain HVAC Services
Installed main supply and return trunk lines in crawl space. Completed air handler platform in utility closet. Began flex duct runs to master bedroom and living room. Approximately 80% complete.
Valley Insulation Inc.
Installed R-15 fiberglass batts in exterior wall cavities, master bedroom (complete), living room (complete). Will return Apr 24 for remaining bedrooms, utility room, and attic floor.
Site Photos
4 photos added today
View all photos →
1 selected
Recent Entries
Click any row to open the past entry
Apr 22
Wed
Framing inspection passed (24/25). Volunteer Electric started rough-in on first floor.
R. Hawkins · submitted 6:12 PM
3 crews · 9 workers
✓ Submitted
Apr 21
Tue
Summit Framing finished second-floor sheathing. Set roof trusses, ready for inspection.
R. Hawkins · submitted 5:38 PM
2 crews · 6 workers
✓ Submitted
Apr 20
Mon
Half-day, rain shut down framing at 11 AM. Plumbers continued under-slab work.
R. Hawkins · submitted 1:24 PM
2 crews · 4 workers
Weather Day
Apr 18
Sat
Saturday make-up day. Summit Framing back on site to make up Friday rain delay.
J. Mitchell · submitted 4:02 PM
1 crew · 4 workers
✓ Submitted
Apr 17
Fri
No work performed. Severe weather cancellation per project schedule.
J. Mitchell · submitted 8:14 AM
0 crews · 0 workers
No Work Day