Backlog 4
Source interior door hardware package
Finishes
JM
Jun 2
Select kitchen cabinet color / style
Finishes
JM
May 28
Order LVL beams for garage header
Framing
RH
May 10
Confirm landscaping bid from Green Thumb
Exterior
JM
Jun 15
To Do 5
Submit Draw #3 to First Tennessee
UrgentFinance
JM
Due Apr 28
Send lien waivers to TK Concrete + Ridgeline
HighFinance
JM
Due Apr 25
Schedule rough-in inspection with Monroe County
HighInspections
RH
Apr 26
Post insulation invoice from Valley Insulation
Finance
JM
Apr 27
Confirm drywall start date with Walls & Ceilings Co.
Scheduling
RH
Apr 30
In Progress 3
Rough-in plumbing · complete all rough-in prior to inspection
HighRough-Ins
65% complete
BW
Apr 29
HVAC rough-in · ductwork + air handler platform
Rough-Ins
80% complete
MT
Apr 26
Insulation installation · batts in ext. walls
Insulation
30% complete
RH
May 4
Done 5
Roofing complete · final walk & signoff
DoneRoofing
JM
Apr 20 ✓
Submit Draw #2 · Framing complete
DoneFinance
JM
Mar 15 ✓
Exterior siding complete · Ridgeline Exteriors
DoneExterior
RH
Apr 14 ✓
Foundation inspection · passed
DoneInspections
RH
Feb 28 ✓
Framing inspection · passed
DoneInspections
RH
Mar 16 ✓