Approval timeline
Submitted by James Mitchell
Apr 23, 2026 · 2:14 PM
Lender pre-draw inspection passed
Apr 24, 2026 · TN-IBC #5024 walk
3
Under credit review (First Community Bank)
In flight, about 1 day remaining
4
Funds wired
3 business days after approval
5
Marketplace contractors auto-paid via Stripe
$47,958 disbursed within 24h of fund clearance
Line items in this draw
Roofing
Internal
$18,200
Architectural shingles, 26 squares. Internal vendor (Appalachian Roofing). Invoice AR-0488 attached.
Rough-in MEP
MC-2026-022
$22,500
Plumbing, electrical, HVAC rough-in via marketplace contract MC-2026-022 (Blue Ridge Plumbing).
Exterior & siding
Internal
$24,800
HardiePlank labor and materials, 2,140 SF, plus trim package. Internal vendor (Ridgeline Exteriors).
Driveway, flatwork
MC-2026-031
$15,600
Final driveway pour, 4 inch reinforced concrete, marketplace contract MC-2026-031 (TK Concrete).
Subtotal$81,100
Less retainage 10%($18,610)
This draw$62,490
Linked records
Open G702/G703 draw form→
Lien waivers (3 of 5 signed)→
Inspection report, Apr 21 walk→