Mobile View, 390px, Day 84
9:14 5G · ●●●●
Builder
Daily Log
926 Stratford, Stratford Builds LLC, Day 84 of 165
Mon, Apr 27, 2026
68°F
Partly cloudy, Sweetwater, TN
Wind 8 mph SW
RH 22%
High 74°
Precip 5%
Crew On Site
JD
James Davidson
General Contractor, Supervisor
8.0 hrs
1
MF
Mike's Framing
Framing Crew
8.0 hrs
4
RE
River Electric Co.
Rough Electrical
6.0 hrs
2
Total, 7 workers, 54.0 man-hours
Work Performed
Framing
Completed north and west exterior wall framing including window rough openings. All headers sized per plan. Fire blocking installed in stair wall per code.
Rough Electrical
River Electric started rough-in on main floor. Panel location confirmed. Ran conduit for kitchen island circuit. Approximately 40% complete.
Photos (6) View All
Materials Used
2x6x16 Lumber84 pcs delivered
OSB Sheathing 7/16"12 sheets used
LVL Beam 3.5"x11.25"1 pc, 16'
Issues and Notes
Framing inspection tentatively scheduled for Apr 29, confirmed with inspector Martin.
09:22 AM, James D.
Garage door header may need to be upsized, waiting on structural engineer callback.
08:40 AM, James D.
Plumber called, rough-in crew on site tomorrow AM. Need to coordinate with electrician.
07:55 AM, James D.
Log Status
Draft Saved
Last saved 9:14 AM, not yet submitted