Marcus and the build team post here as work happens
Today · May 19
MH
Marcus Hale
Builder · 8:14 AM
Milestone
Framing crew started the first-floor walls this morning. We hit the dimensions exactly per the latest A-201 revision. Two of the headers came in pre-cut, so we're already a few hours ahead. Photos below.
+3 more
Friday · May 16
MH
Marcus Hale
2:48 PM
Inspection passed
Foundation inspection passed this afternoon. Loudon County inspector verified the stem walls, perimeter drain, and waterproofing. Cleared to backfill Monday and start framing right after.
Wednesday · May 14
SG
Sarah Gentry
Selections · 11:02 AM
Siding sample board is pinned to the north wall of the build, three Hardie colors. Take a look when you're next on site, samples to your inbox tomorrow if you can't make it out. Reminder, decision needed by Friday May 22.
MH
Marcus Hale
7:14 AM
Foundation walls poured Tuesday, stripped forms Wednesday morning. Walls look clean. Photos attached.
Earlier this month
RP
Rachel Pham
First Tennessee · May 12
Draw 03 approved and funded today. $32,150 transferred to Stratford Custom Homes. Receipt is on your Draws tab.