Milestones and phase timeline · day 142 of build
On schedule
Phase 1 · Site prep & permits · complete
Building permit issued
Loudon County permit #2026-0114-R
Jan 12
Lot cleared and graded
Site ready for excavation
Jan 22
Phase 2 · Foundation · complete
Footings poured
Inspected and passed
Feb 18
Foundation walls and waterproofing
Stem walls, perimeter drain
Apr 28
Foundation inspection
Passed Loudon County
May 15
Phase 4 · Framing · in progress
First-floor walls and roof trusses
Crew on site this week · ~14 days to dry-in
Active
Roof dry-in
Sheathing, underlayment, shingles
Jun 12
Phase 5 · Mechanical rough-in · upcoming
Plumbing rough-in
Drain, waste, vent
Jun 22
Electrical rough-in
Panel, runs, boxes
Jul 02
HVAC rough-in
Ductwork, equipment placement
Jul 12
Phase 6–8 · Finish · upcoming
Insulation and drywall
Phase 6
Aug
Cabinetry, flooring, tile
Phase 7
Sep
Final trim, paint, fixtures, punchlist
Phase 8 · move-in
Nov 08