Builder
Cost trend
Trailing 12 months on materials and trades, East-TN regional
LUMBER PER BF · 12 MO
$0.62You · 44%ile · regional median $0.65
YOU · 44%
$0.50$0.60$0.70$0.80
CONCRETE PER CY · 12 MO
$192You · 28%ile · regional median $178
YOU · 28%
$160$180$200$220
Materials index · trailing 12 months
Trade rate movement
| Trade | Avg rate | 12 mo | 3 mo | Sentiment |
|---|---|---|---|---|
| Framing crew | $38/hr | +2.1% | flat | Stable |
| Concrete sub | $192/cy | +6.2% | +1.8% | Rising |
| HVAC install | $4,200 | +4.0% | +0.4% | Slow rise |
| Electrical rough | $3,100 | -1.2% | -0.8% | Softening |
| Drywall | $1.10/sf | +2.6% | flat | Stable |