12-month rolling forecast
Base-case assumptions
Marketplace contracts auto-pay on schedule (24-48h post-draw); open RFQs award within 3 weeks at mid-band pricing; owner sign-offs follow 5-business-day SLA; loan draws clear in 3 business days.
Net 12-month flow
+$284,720
Across 4 active projects
Min monthly net
-$48,200
Aug 2026 (peak burn)
Marketplace commitments
$294,140
Deterministic outflows
Open RFQ uncertainty
±$32,400
5 RFQs awaiting award
Monthly forecast · May 2026 to Apr 2027
Inflow (draws) MC outflow Internal outflow Uncertainty
+$120k+$60k$0-$60k-$120k MayJunJulAug SepOctNovDec JanFebMarApr
Per-month detail
Click any row for source breakdown
MonthInflow (draws)MC outflowInternal outflowNetNotes
May 2026$48,000$22,400$33,600-$8,000Drywall and insulation phase across 926 and 714
Jun 2026$52,000$24,200$29,800-$2,000Finishes and flooring
Jul 2026$84,000$17,800$24,000+$42,200926 Stratford projected close
Aug 2026$32,000$36,200$44,000-$48,200Peak burn · Maple Ridge framing kickoff
Sep 2026$58,000$24,000$30,000+$4,000Maple Ridge rough-ins
Oct 2026$62,000$20,000$26,000+$16,000Clover Lane finish phase and Maple Ridge exterior
Nov 2026$92,000$14,400$18,200+$59,400714 Clover Lane projected close
Dec 2026$44,000$26,200$32,000-$14,200Maple Ridge interior phase
Jan 2027$38,000$22,400 ±$8k$28,000-$12,400RFQ-2026-117 award pending (electrical)
Feb 2027$54,000$20,000 ±$6k$24,000+$10,000Tentative bid awards land · Maple Ridge finishes
Mar 2027$72,000$18,000 ±$4k$20,000+$34,000Maple Ridge selections and closing prep
Apr 2027$98,000$14,000$16,000+$68,000418 Maple Ridge projected close
12-month total$734,000$259,600$325,600+$148,800Net flow excludes $135,920 retained equity earned