926 Stratford, plumbing rough-inOn schedule
Stratford Custom Homes · Sweetwater · Started May 16 · Crew of 4
$12,400
contract value
Milestones
1Slab penetrationsClosed May 17, $2,000 invoicedDone$2,000
2Underground supplyClosed May 17, $1,200 invoicedDone$1,200
3Walls D0 prepClosed May 18, $1,000Done$1,000
4Walls D1, in progressCrew of 4 on site, target close today 4:00 PMToday$3,200
5Rough-in inspectionThu May 21, 9:30 AMUpcoming$2,000
6Punch list and close outWithin 5 days of inspection passUpcoming$3,000