926 Stratford · The Tennessean
Sweetwater, TN · 1,784 SF · Stick-built spec · PRJ-2026-118
In construction Phase: Rough-In Borrower reliability 4.4
Loan Amount
$322,688
Drawn $214,820 (66.6%)
Project Cost
$430,250
Actual to date $286,420
LTC
75.0%
Within band (65–80%)
Construction Phase Progress
Site & Foundation
Complete
Framing
Complete
Rough-In
In progress
Finishes
Pending
Final / CO
Pending
Recent Borrower Activity
JM
James Mac submitted Draw #4 ($48,250)
12 min ago
Rough-electrical inspection passed (Inspector R. Vance)
1d ago
CO
CO #2 ($4,180) signed by owner · added trim window upgrade
2d ago
$
Marketplace contract MC-2026-014 (Summit Framing) marked complete
4d ago
Borrower Snapshot
Stratford Custom Homes
Sweetwater, TN · 11 active builds with FCB
Reliability
4.4 / 5.0
On-time draws
94%
Avg variance
+1.8%
First worked
2022-Q3
View full builder profile →
Key Documents
Construction Loan Agreement
Signed 2026-02-14 · 28 pp
Title Insurance
Old Republic · effective 2026-02-14
Builder's Risk Insurance
Travelers · expires 2026-08-14
Appraisal
$465,000 (after-build) · 2026-01-08
Budget · High Level (read-only)As of Apr 30, 2026
TradeBudgetActualΔSource
Site preparation$24,800$23,940-3.5%Internal
Foundation$32,400$33,180+2.4%Internal
Framing$58,400$58,400+0.0%Mktp · MC-2026-014
Roofing$22,600$22,600+0.0%Mktp · MC-2026-018
Plumbing rough$14,200$14,840+4.5%Internal
Electrical rough$22,800$23,640+3.7%Bid pending
HVAC rough$18,400·PendingOpen to bid
Total$430,250$286,420+1.8%
Marketplace Spend
$81,000
19% of project cost · 2 contracts
Internal Spend
$282,750
66% · in-house + bid-won subs
Open to Bid
$66,500
15% · HVAC + finishes
Marketplace Contracts
Contract #TradeSubcontractorValuePaidStatusAuto-pay
MC-2026-014 Framing Summit Framing
4.6★ · 38 jobs
$58,400 $58,400 Complete Stripe Connect
MC-2026-018 Roofing Tennessee Roofworks
4.4★ · 22 jobs
$22,600 $13,560 Active Stripe Connect
Open RFQs (Bid in flight)
RFQTradeBidsLo / HiStatus
RFQ-2026-117Electrical rough4 received$21,800 / $24,200Awaiting award
RFQ-2026-129HVAC rough2 received$17,800 / $19,400Open
Source Mix vs. Portfolio Average
Marketplace 19%
Internal 66%
Open 15%
Your portfolio average: Marketplace 24% · Internal 61% · Open 15%. Stratford runs slightly internal-heavy compared to your other borrowers.
Source: 33.4.22 · Lender view of marketplace breakdown. Marketplace contracts are deterministic outflows because the value and pay schedule lock at contract sign; open RFQs and bid-pending lines remain speculative until they award.
Draw History
DrawSubmittedAmountCumulativeStatusReviewer
Draw #12026-02-28$42,820$42,820ApprovedS. Reeves
Draw #22026-03-15$58,180$101,000ApprovedS. Reeves
Draw #32026-04-02$65,570$166,570ApprovedS. Reeves
Draw #42026-04-30 (today)$48,250$214,820Under reviewS. Reeves
Milestone Schedule
Foundation pourComplete · 2026-02-26
Dry-inComplete · 2026-04-08
Insulation inspectionScheduled · 2026-05-12
Drywall completeProjected · 2026-05-28
Final / COProjected · 2026-07-22
Documents · Loan File
Construction Loan Agreement
Signed · 2026-02-14 · 28 pp
Current
Title commitment
Old Republic · 2026-01-22
Current
Builder's risk policy
Travelers · expires 2026-08-14
Expiring 90d
Appraisal
2026-01-08 · ARV $465,000
Current