Contractor
Riverbend 22, plumbing rough-inAthens Endeavours
2,140 SF, 4 bed / 3 bath, slab on grade. RFQ from Athens Endeavours. Bid closes May 29 at 5:00 PM. Plans in BuilderGrid v3, dated May 12.
Line items
| Line item | Unit | Qty | Price | Subtotal | Peer position | |
|---|---|---|---|---|---|---|
| Tub valve, brass | each | 3 | $140 | $420 | Median | |
| Toilet rough, ABS | each | 3 | $120 | $360 | Median | |
| Sink rough, kitchen | each | 1 | $180 | $180 | In range | |
| Sink rough, bath | each | 3 | $140 | $420 | In range | |
| Shower drain, 2" | each | 3 | $110 | $330 | In range | |
| Hose bib, frost-proof | each | 2 | $95 | $190 | Above 75% | |
| PEX manifold, 12 port | each | 1 | $268 | $268 | In range | |
| Slab penetration, sealed | each | 12 | $48 | $576 | In range | |
| Gas line, 1/2" black iron | LF | 24 | $48 | $1,152 | Median | |
| Labor, journeyman | hour | 48 | $62 | $2,976 | Median | |
| Labor, apprentice | hour | 48 | $32 | $1,536 | In range | |
| Subtotal | $8,408 | |||||
| Overhead and margin (15%) | $1,261 | |||||
| Bid total | $9,669 | |||||